The U.S. Department of Energy's Office of Energy Dominance Financing on Nov. 17 announced a conditional loan commitment of up to $2.8 billion for Grid United's Wyoming Intertie project, intended to lower electricity costs and strengthen grid reliability in Wyoming, DOE said.
The project will add approximately 1.8 gigawatts of electricity transfer capacity and is estimated to deliver up to $39 billion in electricity cost savings for American families and businesses across 17 states within the Western Electricity Coordinating Council and Southwest Power Pool regions, the department said. Wyoming Intertie will double existing transfer capacity between the SPP and WECC regions, allowing more electricity to flow across Wyoming to meet growing demand and improve grid resilience during periods of high demand and extreme weather. The project will also create hundreds of construction-related jobs and long-term operations jobs over the 30-year life of the project, DOE said.
The loan advances President Trump's executive order on strengthening the reliability and security of the U.S. electric grid, the release said, and builds on DOE's recent Speed to Power through Accelerated Reconductoring and other Key Advanced Transmission Technology Upgrades, or SPARK, announcement. "The Energy Department is delivering on President Trump's promise to strengthen America's electric grid and unleash American energy dominance," Secretary of Energy Chris Wright said. "Projects like Wyoming Intertie will help move more American energy where it's needed most to support our nation's growing energy needs and power American prosperity for decades to come." EDF Director Gregory A. Beard said the project is an example of how the office's financing can help lower electricity costs, create jobs, and support long-term growth in Wyoming and across the nation.
DOE was careful to describe the announcement as conditional. "While this conditional commitment indicates DOE's intent to provide a loan, Grid United's Wyoming Intertie project must satisfy certain technical, legal, environmental, and financial conditions before the Department enters definitive financing documents and funds the loan." That means the $2.8 billion figure is a ceiling on a commitment that has not yet been funded, not money already disbursed.
The official release does not give a construction start date, a route map, or a list of the 17 states beyond the WECC and SPP regional labels. It also does not say the loan is final. For readers, the sourced facts are the Nov. 17 date, the up-to-$2.8 billion conditional commitment, about 1.8 gigawatts of added transfer capacity, the estimate of up to $39 billion in savings, the doubling of SPP-WECC transfer capacity, the 30-year project life, and the conditions still required before funding.